Village Development Plan of Khawlailung Gram Panchayat (MZSRLM)
Statement I Summary of all Areas of Work
Sl.No |
Area of work |
Sector |
How? (Scheme(s)/ Strategy) |
Line Department /Agency |
Budget (if any) (In Rupees) |
Completion timeline (in months) |
Priority (1 to 3, 1 is top) |
Remarks |
1 |
Contribution of SHGs in Swatch Bharat Mission by placing dustbins in various streets within the village.
|
Cleanliness |
MZSRLM |
Rural Development Department |
2000 |
15 days |
1 |
Cost of project will be met from contribution of PLF |
2 |
Health awareness by distributing pamphlet on Health and personal Hygiene |
Cleanliness |
Mzsrlm |
Rural Development Department |
3,000 |
1 month |
1 |
Cost of project will be met from contribution of PLF |
3 |
Introduction of PMJJBY/PMSBY to all SHG members and application for insurance Policies |
Security |
PMJJBY/PMSBY |
Mizoram Rural Bank /Rural Development Department |
Own contribution |
1 month |
1 |
|
4. |
Assistance of SHGs by providing fund to initiate their activities on various micro enterprises Handloom / tailoring etc |
Livelihood/Microenterprise |
MZSRLM/IWMP |
Rural Development Department |
2,00,000 |
12 months |
1 |
|
5. |
Plantation of trees and flowers by SHG members |
Environment protection |
Acquisition of Saplings from Environment and forest / horticulture Dept |
Rural Development Department/ Environment and Forest Deptt/ Horticulture Dept |
-Rs 2000 |
12 months |
2 |
|
6. |
Training of SHG members on Tailoring/ Handloom |
Capacity Building |
IWMP/NRLM |
Rural Development Department/Industries Dept |
Rs 50,000 |
12 months |
2 |
|
Statement II Detailed of Each Area of Work
1 |
2 |
3 |
4 |
5 |
6 |
7 |
S. No |
Scheme |
Milestones |
Milestone Timelines |
Responsibility |
Outcome |
Remarks |
1 |
Contribution of SHGs in Swatch Bharat Mission by placing dustbins in various streets within the village. |
1. field study |
3 days |
Cluster Coordinator & PLF |
Proper sanitation at Village |
|
2. Collection of Materials, Painting of Dustbins by SHGs |
8 days |
SHG members |
||||
3. Arrangements at village level and execution of work |
15 days |
SHG members |
||||
2 |
Health awareness by distributing pamphlet on Healthy Lifestyle and personal Hygiene
|
1. field study |
3 days |
Cluster Coordinator & PLF |
Improvement on Health and Personal Hygiene of Villagers especially Women which in turn will have positive effect on their family |
|
2. preparation and Printing of Pamphlets |
5 days |
SHG members |
||||
3. Distribution to every household |
30 days |
SHG members |
||||
3 |
Introduction of PMJJBY/PMSBY to all SHG members and application for insurance Policies |
1. field study |
5 days |
Cluster Coordinator & PLF/ MRB Officials |
100% Insurance Coverage of SGH members (women) |
|
2. Awareness among SHG members on Importance of SHGs |
15 days |
Cluster Coordinator & PLF/ MRB Officials |
||||
3.Application of Insurance Policy at Bank ( E.Lungdar MRB) |
20 days |
SHG members/Bank Personnel |
||||
4 |
Plantation of trees and flowers by SHG members
|
1. field study |
3 days |
Cluster Coordinator & PLF |
Biodiversity conservation and Beautification of Village.
|
|
2 Coordination with line departments |
4 days |
Cluster Coordinator & PLF |
||||
3.Plantation of Trees at Various places within the Village |
30 days |
SHGs members |
||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
S. No |
Scheme |
Milestones |
Milestone Timelines |
Responsibility |
Outcome |
Remarks |
5 |
Assistance of SHGs by providing Revolving fund / fund for micro enterprises to initiate their activities on Handloom / tailoring etc |
1. field study/ selection of beneficiaries/ Grading |
1 month |
PLF/CC and Watershed Committee members IWMP |
Improvement on Livelihood and self employment |
|
2. Preparation and submission of Proposals to higher authorities |
3 months |
Cluster coordinators and WDT |
||||
3.Execution at Village Level |
12 months |
PLF/CC/WDT/WC members/SHGs members |
||||
6 |
Training of SHG members on Tailoring/ Handloom |
1. field study/ selection of Trainees |
1 month |
PLF/CC and Watershed Committee members IWMP ( Convergence of schemes) |
Improvement on Livelihood and self employment |
|
2. Preparation and submission of Proposals to higher authorities |
4 months |
Cluster coordinators and WDT |
||||
3.Execution at Village Level |
12 months |
PLF/CC/WDT/WC members/SHGs members |